4. Installation
4.1 Handling and Unpacking
This section describes the required safe handling and unpacking procedures for the
PVP250kW and PVP260kW Inverters. Always follow the recommendations in this
section to prevent accidental damage or injury.
!
WARNING
Heavy Equipment. PVP250kW and PVP260kW Inverters weigh up to 5,200
pounds with pallet and packaging. If the inverter is lifted incorrectly, it may
result in death. In addition, improper handling may result in serious damage
to the inverter and may also void the warranty. Keep all doors securely closed
while moving the inverter. Only use lifting equipment that is rated for the
weight of the inverter. Only use the specied lifting points.
!
AVERTISSEMENT
Équipement lourd. Les onduleurs de modèles PVP250kW et PVP260kW,
les palettes les supportant et leur emballage pèsent un maximum de 2 270
kg. Un levage incorrect de l’onduleur peut entrainer la mort. De plus, une
manipulation inadéquate est susceptible d’endommager gravement l’unité et
d’annuler la garantie. Assurez-vous que toutes les portes sont bien fermées
avant de déplacer l’onduleur. Utilisez seulement un équipement homologué
pour lever l’onduleur. Utilisez seulement les points de levage spéciés.
Handling
The inverter can be handled using a forklift or pallet jack that is rated to handle a
minimum of 5,000 pounds.
To unload the inverter from the delivery vehicle onsite:
Lift and move the inverter using the shipping pallet. Do not penetrate the packaging
or use the inverter base for unloading.
Leave the inverter on its shipping pallet with its protective plastic wrap in place
to alleviate any UV concerns if it is stored outside, until it is time to install.
When the inverter is ready to be placed in its mounting location, complete the following
steps:
1. Remove the protective plastic wrap.
2. Remove all bolts that anchor the inverter to the pallet.
3. Plan for a safe move by rst considering the inverters center of gravity.
Note: The center of gravity is toward the back, lower third of the inverter and
centered side to side. See Appendix C
- Mechanical Drawings
to view the center
of gravity location.
INSTALLATION